Information:
Road Watch
Check
for Road Watch on Google Maps
Road Watch for the
Week of:
October
13, 2008
September
29,
2008
|
View Larger Map
|
|
|
OTHER |
CITY
OF MARYSVILLE - Construction on Busha Highway (M-29) is scheduled
to begin the week of September 1, 2008. Construction
includes storm sewer installation, concrete pavement widening,
concrete curb & gutter, HMA shoulder surfacing, bike path
construction & site restoration from Old River Road to Wills
Street. Road traffic on Busha Highway will not be detoured,
however, lane closures are to be expected if traveling through
this area. The contract completion date is October 31, 2008. CITY
OF MARYSVILLE - There will be intermittent lane closures on
Gratiot Road between I-94 and M-29 for crack sealing during the
week of 10/06/08.
CITY
OF MARYSVILLE - Construction on Busha Highway (M-29) is scheduled
to begin the week of September 1, 2008. construction
includes storm sewer installation, concrete pavement widening,
concrete curb & gutter, HMA shoulder surfacing, bike path
construction & site restoration from Old River Road to Wills
Street. Road traffic on Busha Highway will not be detoured;
however, lane closures are to be expected if traveling through
this area. The contract completion date is October 31, 2008. CITY
OF MARYSVILLE - There will be intermittent lane closures on
Gratiot road between I-94 and M-29 for crack sealing during the
week of 10/13/08. CITY
OF MARYSVILLE - There will be intermittent lane closures on M-29
between Gratiot Road and Bunce Road for crack sealing during the
week of 10/13/08.
|
|
2007 Sealcoat |
No Closures
|
|
Berlin |
No Closures
|
| Brockway |
No Closures
|
| Burtchville |
There
will be intermittent lane closures on M-25 between Fisher Road and
Burtch Road for crack sealing during the week of 10/13/08.
|
| Casco |
There
will be intermittent lane closures on Palms Road between Marine
city Highway and Lindsey Road for crack sealing during the week of
10/06/08.
|
| China |
No Closures
|
|
Clyde |
No Closures
|
| Clay |
No Closures
|
| Columbus |
There
will be intermittent lane closures on Dolan and Rattle run Roads
between Mayer Road and Bordman Road for wedging during the week of
10/06/08.
|
| Cottrellville |
No Closures
|
| East China |
No Closures
|
|
Emmett |
There
will be intermittent lane closures on Westbound I-69 Road between
M-19 to Miller road for crack sealing during the week of 10/13/08.
|
| Fort Gratiot |
No Closures
|
| Grant |
Construction
on the Jeddo Road Bridge will begin August 11, 2008.
Construction includes removing the existing steel and concrete
bridge, tree removal, removal of existing foundation, placing new
concrete abutment walls, placing new concrete box beams, placing
new concrete deck, installing new railing, rebuilding the road
approaches on each side of the bridge and upgrading road
drainage. The road will remain closed to all through
traffic. The road will remain open to local traffic on
either side of the bridge. The contract completion date is
October 10, 2008
Construction
on the Jeddo Road Bridge will begin August 11, 2008.
Construction includes removing the existing steel and concrete
bridge, tree removal, removal of existing foundation, placing new
concrete abutment walls, placing new concrete box beams, placing
new concrete deck, installing new railing, rebuilding the road
approaches on each side of the bridge and upgrading road
drainage. The road will remain closed to all through
traffic. The road will remain open to local traffic on
either side of the bridge. The expected completion date is
November 7, 2008.
|
| Greenwood |
No Closures
|
| Ira |
No Closures
|
|
Kenockee |
No Closures
|
| Kimball |
There
will be a lane closure on Eastbound I-69 between Taylor road and
Wales Center Road for concrete patching during the week of
10/13/08.
|
| Lynn |
No Closures
|
| Mussey |
There
will be intermittent lane closures on Capac Road between Downey
Road and Sterling Road for crack sealing during the week of
10/06/08.
|
| Port Huron |
Construction
at the Lapeer Road and Michigan Road intersection is scheduled to
begin the week of September 8, 2008. Construction includes
intersection widening for a center left turn lane on Lapeer Road
at Michigan Road. The road will be open to through traffic,
however, lane closures and flag people will be needed to complete
the construction. The project is expected to last
approximately four to six weeks.
Construction
at the Lapeer Road and Michigan Road intersection is scheduled to
begin the week of September 8, 2008. construction includes
intersection widening for a center left turn lane on Lapeer Road
at Michigan Road. The road will be open to through traffic,
however, lane closures and flag people will be needed to complete
the construction. The expected completion date is October
17, 2008.
|
| Riley |
Belle
River Road just east of Riley Center Road will be closed to
through traffic for cross road culvert replacement on 10/06/08 and
10/07/08.
There
will be intermittent lane closures on Westbound I-69 Road between
M-19 to Miller road for crack sealing during the week of 10/13/08.
|
| St. Clair |
Wadhams
Road over I-94 will be closed for new approach and deck
construction from 7/21/08 through 10/10/08. Visit www.michigan.gov/mdot
for updated information. Construction
on Busha Highway (M-29) is scheduled to begin the week of
September 1, 2008. Construction includes storm sewer
installation, concrete pavement widening, concrete curb &
gutter, HMA shoulder surfacing, bike path construction & site
restoration from Old River Road to Wills Street. Road
traffic on Busha Highway will not be detoured, however, lane
closures are to be expected if traveling through this area.
The contract completion date is October 31, 2008.
Wadhams
road over I-94 will be closed for new approach and deck
construction from 7/21/08 through 10/26/08. Visit www.michigan.gov/mdot
for updated information. Construction
on Busha Highway (M-29) is scheduled to begin the week of
September 1, 2008. construction includes storm sewer
installation, concrete pavement widening, concrete curb &
gutter, HMA shoulder surfacing, bike path construction & site
restoration from Old River Road to Wills Street. Road
traffic on Busha Highway will not be detoured; however, lane
closures are to be expected if traveling through this area.
The contract completion date is October 31, 2008.
|
| Wales |
There
will be intermittent lane closures on Alpine Road between Wales
Ridge Road and Fitz Road for wedging during the week of 10/06/08. There
will be intermittent lane closures at the intersection of Smiths
Creek Road and Wales Center Road for paving during the week of
10/06/08.
There
will be a lane closure on Eastbound I-69 between Taylor road and
Wales Center Road for concrete patching during the week of
10/13/08.
|
|
|
|
|
|
|
Information
Request
for Proposals / Employment
/ Weight
Limits / Class
A Roads / Maps
/ FAQ's
/ Closed
Roads / Policies
/ Adopt-a-Highway
/ Brochures
Home
Copyright
2000
St. Clair County Road Commission
Page
Updated: October 06, 2008
|
| |
 |
 |
 |
|
Copyright ©2002 All rights