Project:  Rattle Run
PROJECT  
Road Rattle Run
Between Palms Road to  Wales Center Road
Description Single Chip Seal and Fog Seal
Township Columbus
Length 2.05 Miles
FUNDING
SCCRC Funding: $ 67,488
Township/County: $ 0
Federal: $ 0
RC Millage Funds: $ 0

Total Project Cost:

$ 67,488
PROJECT DATES  
Anticipated Bid: Annual Bid
Anticipated Start: June 2017
Anticipated Completion: August 2017
MISCELLANEOUS  
Contractor Fahrner Asphalt Sealers
Notes:  
Project Status:  
   
All amounts and dates are estimates unless otherwise noted.

 