Project:  Shortcut Road
PROJECT  
Road Shortcut Road
Between Starville Road east 0.75 miles
Description 2" HMA Overlay
Township Cottrellville
Length 0.75 miles
FUNDING
SCCRC Funding: $ 49,000
Township/County: $ 45,000
Federal: $ 0
RC Millage Funds: $ 0

Total Project Cost:

$ 94,000
PROJECT DATES  
Anticipated Bid: January 2017
Anticipated Start: June 2017
Anticipated Completion: August 2017
MISCELLANEOUS  
Contractor Ace-Saginaw Paving
Notes:  
Project Status: Project Complete
   
All amounts and dates are estimates unless otherwise noted.

 