Project:  Puttygut Road
PROJECT  
Road Puttygut Road
Between Wadhams Road to King Road
Description 1.5" HMA Overlay
Township China
Length 2.00 miles
FUNDING
SCCRC Funding: $  106,000
Township/County: $  99,500
Federal: $ 0
RC Millage Funds: $ 0

Total Project Cost:

$  205,500
PROJECT DATES  
Anticipated Bid: January 2017
Anticipated Start: June 2017
Anticipated Completion: August 2017
MISCELLANEOUS  
Contractor Ace-Saginaw Paving
Notes:  
Project Status:  
   
All amounts and dates are estimates unless otherwise noted.

 