Project:  Wales Center Culvert
PROJECT  
Road Wales Center
Between Lambs Road and Lashbrook Road
Description Replacement
Township Wales
Length N/A
FUNDING
SCCRC Funding: $ 36,945
Township/County: $ 0
Federal: $ 42,055
RC Millage Funds: $ 22,945

Total Project Cost:

$ 79,000
PROJECT DATES  
Anticipated Bid: N/A
Anticipated Start: September 2016
Anticipated Completion: October 2016
MISCELLANEOUS  
Contractor Road Commission Staff
Notes:  
Project Status:  
   
All amounts and dates are estimates unless otherwise noted.

 