image
image



Project:  Tubspring Culvert
PROJECT  
Road Tubspring Road
Between Wheeleer Road and Capac Road
Description Replacement
Township Berlin
Length N/A
FUNDING
SCCRC Funding: $ 17,500
Township/County: $ 13,500
Federal: $ 0
RC Millage Funds: $ 0

Total Project Cost:

$ 31,000
PROJECT DATES  
Anticipated Bid: N/A
Anticipated Start: June 2016
Anticipated Completion: July 2016
MISCELLANEOUS  
Contractor Road Commission Staff
Notes:  
Project Status: Project Complete
   
All amounts and dates are estimates unless otherwise noted.

 